BT Murrayfield Stadium
Scottish Rugby Union
STATISTICS
LOCATION
Edinburgh
DURATION
8 Months
VALUE
£1.5m
This project involved the strip out and replacement of the boilers within the North, South and West Stands and Undersoil plantrooms at Murrayfield.
As well as the installation of the boilers and new heating pipework arrangement, the other mechanical works we delivered, included the installation of the updated gas systems and automatic controls, all of which were also commissioned by ourselves. As BT Murrayfield stadium is a live arena, it was crucial to have excellent communications with the client in order to programme and schedule around stadium events to ensure there were no delays or disruption.